Construction progress of the Second building
Construction progress of the Second building
Esteemed Participants!
We are informing you about the progress of the second building construction.
On the 26th October 2016, the company “DM Holding” cleared the first step of the construction process – preparation of the construction site.
At the moment, we have finished relaying outer networks, such as:
-Gas pipelines
-Heating networks
-Electric networks 10 kV
At the moment, we have begun the second step of the construction process, which includes:
-We have developed all of the project and working documentation
-received technical conditions about technical-engineering provision of the building
This stage also includes:
-Setting up of the temporary road access and parking
-Setting up temporary electricity networks
-Setting up temporary water supply
-Securing and Isolating the construction site
In the first decade of November 2016 “DM Holding” will begin the process of digging to set up the foundation construction.